Permanent Building Committee approves four project payments totaling $730,494.36.
Wellesley Permanent Building Committee approves $730,494 across four projects in single meeting. Michael Tauer, Chair, and four of five members voted unanimously on requisition payments for Hardy School solar project ($288,052.05), Warren Building HVAC work ($222,992.59 and $21,488.34 change